Malaysia to install 1,250 MW of solar PV by 2020
In March 2016 MIDA projected Malaysia would reach about 1,250 MW of solar PV by 2020, up from 230 MW, through net energy metering and large-scale solar. How the plan was built.
In March 2017 a Malaysian deputy minister told Parliament the PV industry could generate RM70 billion and 50,000 jobs by 2020. Who said it, and how it compared with the data.
In March 2017 Malaysia’s Deputy Minister of Science, Technology and Innovation, Datuk Dr Abu Bakar Mohamad Diah, told the Dewan Rakyat that the country could potentially generate RM70 billion and 50,000 jobs from the photovoltaic (PV) industry by 2020. The statement, reported by Bernama, was an answer to a parliamentary question rather than a published plan, and it should be read as a projection of potential. Set against the industry data available at the time, it implied very rapid growth.
The deputy minister was answering a question from Dr Rosli Che Mat, MP for Hulu Langat, about the development of thin-film technology and its contribution to the industry. According to the Bernama report, he:
The report did not say whether RM70 billion meant annual revenue in 2020 or a cumulative total over several years, nor how the jobs figure was derived. Those gaps matter when judging the projection.
The deputy minister listed eight PV production companies:
| Company | Location named in the answer |
|---|---|
| First Solar | Kulim Hi-Tech Park, Kedah |
| Panasonic Energy Malaysia | Kulim Hi-Tech Park, Kedah |
| JA Solar | Penang |
| Jinko Solar | Penang |
| TS Solartech | Penang |
| SunEdison | Ipoh, Perak |
| SunPower | Melaka |
| Q-Cells Malaysia | Cyberjaya, Selangor |
All were foreign-owned or foreign-linked, continuing the pattern described in our restored article on international PV manufacturers in Malaysia.
Two published figures give a baseline.
If RM70 billion is read as annual revenue in 2020, the required growth from the 2015 level is:
Growth factor = 70 / 20.8 ≈ 3.37
Annual growth = 3.37^(1/5) − 1 ≈ 0.27, or about 27% per year for five years
Reaching 50,000 jobs from about 21,700 would similarly require the workforce to grow by a factor of about 2.3. Neither is impossible for a manufacturing sector attracting new factories, but both are demanding for an export industry exposed to global price swings and trade measures.
If instead RM70 billion was meant cumulatively over 2016–2020, it would correspond to an average of RM14 billion a year, below the reported 2015 revenue. The ambiguity makes the projection hard to test.
The RM70 billion figure had appeared before. In October 2010, ahead of Malaysia’s feed-in tariff, a technical adviser to the Malaysia Building Integrated Photovoltaic project was reported as estimating that renewable power could generate about RM70 billion in revenue by 2020 and about 52,000 jobs building, operating and maintaining renewable plants. That earlier estimate covered renewable energy generation broadly, not PV manufacturing. The similarity is a reminder that headline projections often travel between contexts, and that their scope should be checked before they are compared.
The projection related to manufacturing, which was overwhelmingly for export. Domestic deployment remained small: only 31.78 MW of solar was added under the feed-in tariff in 2016, bringing cumulative FiT solar capacity to 294.85 MW. A larger manufacturing base did not by itself create a larger local solar market: factory output was sized for export demand, while domestic installations depended on tariff quotas and tenders.
The domestic market did begin to grow after 2017 through large-scale solar tenders and net energy metering. SEDA’s NEM programme, introduced in November 2016 with a 500 MW quota, was followed by NEM 2.0 from 2019 and NEM 3.0 from 2021. Readers wanting to check how revenue and employment actually developed against the 2017 projection should consult the later IEA PVPS national survey reports for Malaysia, such as the 2019 edition, which use consistent definitions year to year. The 2012 consolidation that preceded this period is described in PV module consolidation in 2013–2014.