Renewable energy incentives in Malaysia (2011): FiT, the RE Fund and tax breaks

How Malaysia's renewable energy incentives stood in mid-2011: the gross feed-in tariff for solar, the Renewable Energy Fund surcharge, and tax and duty exemptions for RE generators.

Line illustration for Renewable Energy

By May 2011 Malaysia’s new renewable energy framework had passed Parliament and was days away from royal assent. Prospective solar homeowners and investors were trying to work out exactly what they would be paid, who would pay it, and what other support was available. This article sets out the main incentives as they stood in mid-2011, beginning with a point that caused early confusion: whether the feed-in tariff paid for all the energy a solar system produced, or only the surplus sent to the grid.

1. The feed-in tariff pays for every kilowatt-hour generated

Some early explanations, including the April 2011 article at this address (see generate electricity at home and earn), described the scheme as net metering. That was not how it was implemented. Under the Renewable Energy Act 2011, the distribution licensee (TNB in Peninsular Malaysia, SESB in Sabah) pays the feed-in approval holder the FiT rate for the renewable energy generated by the installation. In practice the solar system has its own FiT meter, and SEDA’s guidance describes the monthly payment as the change in that meter’s reading multiplied by the FiT rate. The household’s own consumption continues to be billed separately at the normal tariff.

Example of the difference

Assume, purely for illustration, a home that generates 400 kWh of solar electricity in a month and consumes 500 kWh.

  • Gross FiT (as adopted): the household is paid 400 kWh × FiT rate and is billed for all 500 kWh at the domestic tariff.
  • Net metering (as first described): the household would be billed only for 500 − 400 = 100 kWh, and receive no premium payment.

With the 2012 rooftop rate of RM1.49 per kWh (basic RM1.23 plus RM0.26 building bonus), the gross FiT payment in this example is RM596 for the month, independent of the household’s consumption.

The 2011 Schedule of rates for solar PV

The Schedule to the Act fixed the following first-year solar rates, each with a 21-year effective period and an 8% annual degression for new entrants:

Installed capacity Basic rate (RM/kWh)
Up to and including 4 kW 1.23
Above 4 kW to 24 kW 1.20
Above 24 kW to 72 kW 1.18
Above 72 kW to 1 MW 1.14
Above 1 MW to 10 MW 0.95
Above 10 MW to 30 MW 0.85

Bonus rates were added for installation on buildings (+0.26), use as building materials (+0.25), locally made modules (+0.03) and locally made inverters (+0.01). Other technologies had their own rates: for example, small hydro up to 10 MW received RM0.24 per kWh for 21 years with no degression, and biomass up to 10 MW RM0.31 per kWh for 16 years.

2. The Renewable Energy Fund

FiT payments are not funded by the utility’s own revenue. Under the Act, the distribution licensee recovers from a Renewable Energy Fund, administered by SEDA, the difference between the FiT it pays and the “displaced cost” of generating the same energy conventionally. The Act allows the Minister to order distribution licensees to pay a portion of their electricity tariffs into the Fund.

In the event, a 1% charge on electricity bills took effect from December 2011, collected by TNB on SEDA’s behalf. Domestic consumers using 300 kWh a month or less, roughly a bill of RM77 or under, were exempt. Because the size of the Fund limited how much renewable capacity could be paid for, SEDA allocated FiT capacity through quotas, a feature that shaped the scheme for the rest of its life.

3. Tax and duty incentives for renewable energy generators

Alongside the FiT, existing fiscal incentives for companies generating energy from renewable sources remained available. According to SEDA’s summary, a locally incorporated company could choose either:

  • Pioneer Status: income tax exemption on 100% of statutory income for 10 years; or
  • Investment Tax Allowance (ITA): 100% of qualifying capital expenditure incurred within 5 years, which could be set off against 100% of statutory income in each year of assessment;

plus import duty and sales tax exemption on renewable energy generating equipment not produced locally, and sales tax exemption on equipment bought from local manufacturers. Under the Budget 2011 announcement, these incentives were extended to applications received until 31 December 2015.

Budget 2011 also extended import duty and sales tax exemptions on solar PV system equipment to registered third-party distributors, including PV service providers approved by the Energy Commission, so that the exemption could reach equipment installed for other users. That incentive expired on 31 December 2012.

These incentives applied to companies. Individual homeowners benefited from them only indirectly, through lower equipment prices; their main incentive was the FiT itself.

4. Bank financing

In mid-2011 there was no dedicated home solar loan product on the market. Prospective homeowners generally had to fund systems from savings or general-purpose borrowing, which was widely seen as a barrier to uptake. The first bank product designed specifically for home PV under the FiT appeared in June 2013 (see loans for home solar PV systems).

What has changed since

The FiT began on 1 December 2011. The RE Fund surcharge rose from 1% to 1.6% on 1 January 2014, when it was applied to SESB customers in Sabah for the first time and the FiT was extended to Sabah. Solar FiT rates fell steeply through degression and rate revisions in 2013–2014 as module prices dropped. For new solar systems the FiT was replaced by net energy metering from November 2016, later by NEM 2.0 and NEM 3.0, and in Peninsular Malaysia by Solar ATAP from 1 January 2026. Malaysia’s later solar targets, such as 1,250 MW of solar PV by 2020, were pursued largely through competitive large-scale solar tenders rather than feed-in tariffs.

Sources and further reading

  1. Renewable Energy Act 2011 (Act 725), FAOLEX / Government of Malaysia
  2. Incentives for End-Users (archived), SEDA Malaysia
  3. Incentives for Importers / Third Party Distributors (archived), SEDA Malaysia
  4. TNB clarifies 1% additional charge for Renewable Energy Fund, Tenaga Nasional Berhad
  5. Feed-in Tariff (FiT) in Malaysia brochure, SEDA Malaysia