Loans for home solar PV systems: Malaysia's first solar financing (2013)
In June 2013 Malaysia's first bank loan designed for home solar PV under the feed-in tariff was launched with SEDA. The terms, the reasons, and a worked repayment example.
In March 2016 MIDA projected Malaysia would reach about 1,250 MW of solar PV by 2020, up from 230 MW, through net energy metering and large-scale solar. How the plan was built.
In March 2016 the Malaysian Investment Development Authority (MIDA) said Malaysia expected to have about 1,250 MW of solar PV installed by 2020, up from roughly 230 MW at the time. The statement, made by MIDA deputy chief executive Datuk Phang Ah Tong and carried by Bernama and The Star, tied the increase to two new government mechanisms: net energy metering for rooftop systems and competitively tendered utility-scale solar. It was a projection by an investment agency, not a binding target, but it reflected programmes that were already being prepared.
According to the March 2016 report, MIDA:
MIDA also repeated the government’s claim that Malaysia was the world’s third-largest manufacturer of PV cells. Our restored article on international PV manufacturers in Malaysia explains how that industry was built.
The 230 MW figure matches official data. The IEA PVPS National Survey Report for Malaysia, prepared with SEDA, put cumulative grid-connected PV under the feed-in tariff (FiT) at 230.48 MW at the end of 2015. Most of it had been installed in three years:
| Period | Grid-connected PV added (MW) |
|---|---|
| Before 2013 | 31.58 |
| 2013 | 107.01 |
| 2014 | 65.06 |
| 2015 | 26.83 |
| Total, end-2015 | 230.48 |
Annual additions were already falling, so reaching a much larger total by 2020 depended on new mechanisms rather than on the FiT alone.
Net energy metering (NEM). The national survey report described NEM as a scheme to be run by SEDA, allowing consumers to generate much of their own electricity on site. It was to total up to 500 MW, offered at 100 MW a year from 2016, divided 10% for domestic, 45% for commercial and 45% for industrial users, complementing and eventually replacing the FiT for solar.
Large-scale solar (LSS). The Energy Commission was to run competitive bidding for solar plants, with 250 MW of capacity allocated each year from 2017 to 2020: 200 MW in Peninsular Malaysia and 50 MW in Sabah. That implied 1,000 MW of LSS by 2020. In March 2016, the same month as MIDA’s statement, the Energy Commission issued a pre-qualification notice for prospective LSS bidders.
A simple sum shows the projection was not the arithmetic total of the quotas:
Existing FiT PV (end-2015) ≈ 230 MW
NEM quota to 2020 = 500 MW
LSS allocations 2017–2020 = 1,000 MW
Sum if every quota were built ≈ 1,730 MW
MIDA projection for 2020 ≈ 1,250 MW
The sources do not explain the gap. It is consistent with an expectation that not every quota would be taken up or connected by 2020, since LSS capacity awarded in a given year would take time to build.
For Malaysia, crossing 1 GW would have marked a shift from a country that manufactured PV for export to one that also used it at scale. LSS also introduced competitive tariffs: rather than receiving a fixed, administratively set rate, developers would bid the price at which they would sell electricity. That was a departure from the premium-payment approach used earlier in the region, such as the adder that supported Thailand’s 7.5 MW solar farm in Nakhon Ratchasima in 2012.
Both mechanisms went ahead, and LSS drew more interest than planned.
The wider industry projections made in the same period are examined in our restored article on the RM70 billion PV industry projection for 2020.