Malaysia to raise electricity tariff by 10% to 20% in 2014
In November 2013 Malaysia's energy minister signalled a 10%-20% electricity tariff rise for 2014. The background, Sabah's position, and the 1 January 2014 increase that followed.
In September 2012 Bangladesh picked Tenaga Nasional's proposal for a 1,320 MW imported-coal plant in a joint venture with BPDB. What was planned, and how the Maheshkhali project ended.
In early September 2012, Bangladeshi media reported that the country’s Power Division had selected a proposal from Malaysia’s Tenaga Nasional Berhad (TNB) to build and operate a 1,320 MW coal-fired power plant. The plant would burn imported coal and be owned by a joint-venture company of the Bangladesh Power Development Board (BPDB) and TNB. It came a year and a half after a proposed coal plant in Sabah had been abandoned, which made it a notable move abroad for a Malaysian utility.
The Star, citing Bangladesh’s New Age newspaper, reported on 5 September 2012 that:
The report did not give a cost or an ownership split; those were set out only when memoranda were signed two years later. At the time Bangladesh was planning several large coal plants to relieve chronic power shortages.
The Malaysian context was pointed. In February 2011 the Sabah government had dropped a proposed 300 MW coal plant at Lahad Datu after years of opposition, and opted for gas instead (see the article on the Kimanis gas-fired plant). Bangladesh offered TNB a large coal project where demand was high and political support, at least initially, was strong.
The 2014 agreements described two 660 MW units. A rough estimate shows the scale of the fuel and emissions involved. Assume full load, a net efficiency of 40% and imported bituminous coal of 25 GJ per tonne (illustrative figures):
Fuel heat input = 1,320 MW / 0.40 = 3,300 MW = 3.3 GJ/s
Per day: 3.3 GJ/s × 86,400 s ≈ 285,000 GJ
Coal: 285,000 GJ / 25 GJ/t ≈ 11,400 t/day
That is close to the 11,000 tonnes a day quoted when the memorandum of understanding was signed in 2014. Using the IPCC default emission factor for bituminous coal of about 94.6 t CO₂ per TJ:
CO₂ per day ≈ 285 TJ × 94.6 t/TJ ≈ 27,000 t
CO₂ per year at an 80% capacity factor ≈ 27,000 × 365 × 0.8 ≈ 7.9 million t
Several bulk carriers a month would be needed to supply the plant, which is why deep-water coastal sites such as Maheshkhali were favoured.
On 21 September 2014, Bangladesh and Malaysia signed a government-to-government MoU, and the BPDB signed a separate MoU with a consortium of TNB and Powertek Energy for a 2 × 660 MW plant on 550 acres at Maheshkhali. The Daily Star reported an initial cost estimate of about US$2 billion; the New Straits Times put it at RM6 billion. The venture was to be 50:50, financed on a non-recourse basis, with the BPDB as sole buyer of the power under a long-term agreement. The MoU was valid for two years unless extended or replaced by a definitive agreement.
For a comparison with gas-fired generation in the region at the same time, see the profile of Thailand’s Wang Noi combined-cycle plant.
The plant was never built.