The Green MechanicsEnergy, engineering and sustainable mobility

Malacca to build its first state-owned solar farm: the RM46 million, 5 MWp Rembia project (2012)

In August 2012 Melaka broke ground on a 5 MWp, RM46 million solar farm at Rembia, built by state-owned Kumpulan Melaka Bhd. What was planned, the numbers checked, and what was built.

Line illustration for Malaysia Energy Archive

In August 2012 the Melaka state government broke ground on what it described as the first solar farm in Malaysia to be built and operated by a state government. The 5 MWp photovoltaic (PV) plant, costing RM46 million, was to rise at the Melaka World Solar Valley in the Rembia Industrial Area near Alor Gajah and sell all of its output to Tenaga Nasional Berhad (TNB) under the national feed-in tariff (FiT). This article sets out what was announced, checks the numbers that circulated at the time, and records what happened next.

The announcement

The ground-breaking took place on 3 August 2012, and the New Straits Times reported it the next day. The key points were:

  • Developer: Kumpulan Melaka Berhad (KMB), a company wholly owned by the Melaka Chief Minister Incorporated.
  • Cost and financing: RM46 million in total, including a RM41 million loan from Malaysia Debt Ventures Berhad, a company owned by the Ministry of Finance Incorporated. The financing agreement was signed at the ground-breaking.
  • Offtake: all electricity to be sold to TNB and fed into the grid.
  • Expected return: then Chief Minister Datuk Seri Mohd Ali Rustam said the state expected a profit of RM73 million over 21 years after servicing the loan, matching the 21-year FiT period for solar PV.
  • Policy context: the project was part of Melaka’s goal of becoming a “green technology city state” by 2020. Two more solar farms were proposed, in Jasin and at the Krubong landfill.

The plant was to be built in three phases:

Phase Capacity Planned grid connection
1 1.30 MWp 15 December 2012
2 1.22 MWp 15 January 2013
3 2.48 MWp 15 February 2013
Total 5.00 MWp

Checking the numbers

Energy, not power

The Chief Minister was quoted as saying the plant would supply “17MW a day”, 514 MW a month and 6,162 MW a year. These are energy figures, so the correct units are megawatt-hours (MWh): about 17 MWh a day, 514 MWh a month and 6,162 MWh a year.

Dividing the annual estimate by the plant’s rating gives its expected specific yield:

6,162,000 kWh ÷ 5,000 kWp ≈ 1,232 kWh/kWp per year
1,232 ÷ 365 ≈ 3.4 kWh/kWp per day

That is a cautious but realistic figure for a ground-mounted plant on the west coast of the peninsula, and close to the 1,200 kWh/kWp per year that SEDA Malaysia used in its own FiT planning examples. For how location affects yield, see annual solar radiation in different Malaysian cities.

The site area

The same report gave the site as 7,248.43 hectares, which would be more than 72 square kilometres for a 5 MWp plant. That cannot be right: it would mean less than 1 kWp per hectare. The figure was almost certainly a misplaced decimal point. Later reports gave the site as about 7.2 hectares, or roughly 1.4 hectares per megawatt-peak.

What the tariff band meant

A 5 MWp plant fell into SEDA’s “above 1 MW up to 10 MW” solar band, which carried much lower rates than home systems. SEDA’s basic rate for that band in 2013 was RM0.7600 per kWh, against RM1.1316 for rooftop systems of up to 4 kW. Bonuses for locally made modules and inverters were available, so the plant’s economics depended on scale rather than a premium rate. For the rooftop side of the scheme at the time, see homeowners can apply for solar rooftop FiT quota.

Was it built?

Yes, although later than first planned. Figures reported from the operator’s site information give the initial operation dates as:

Phase Capacity Initial operation
1 1.30 MWp 11 April 2013
2 1.22 MWp 16 May 2013
3 2.48 MWp 2 August 2013

The same report gives the total investment as RM46 million, broken down as RM38 million for the PV system, RM2 million for infrastructure and RM6 million for land, with exports to TNB and a payback period of 12 years. Each phase therefore started about four to six months behind the schedule announced in 2012.

Why it mattered in 2012

When the plant was announced, Malaysia’s FiT was less than a year old, having started on 1 December 2011. A state-owned company borrowing against a guaranteed 21-year tariff showed that a public body could treat a solar farm as a revenue-earning asset rather than a demonstration project. Melaka paired the plan with other green-technology projects, including the electric bus it launched in 2014.

What has changed since

  • Scale. A 5 MWp plant was significant in 2012, but national targets soon moved to far larger volumes; see Malaysia to install 1,250 MW of solar PV by 2020.
  • Melaka’s own portfolio. In April 2026 the state said its earlier solar farms at Ayer Keroh, Rembia, Bemban and Masjid Tanah together generate about 102 GWh a year. It announced a RM437 million, 90 MWac hybrid floating solar project at the Jus Dam in Jasin.
  • Policy. Net energy metering became the main route for new rooftop solar from November 2016. Plants that started under the FiT, such as Rembia, keep their 21-year terms; for the first phase that runs to 2034.

Sources and further reading

  1. Malacca to build solar farm (4 August 2012, archived), New Straits Times
  2. SEDA Malaysia home page with 2013 and 2014 FiT rates (archived May 2013), SEDA Malaysia
  3. Feed-in Tariff (FiT) in Malaysia brochure, SEDA Malaysia
  4. KMB 5 MWp solar farm (site visit report, 21 October 2019), EE Tech News, Faculty of Electrical Engineering, UiTM Dungun
  5. Melaka to develop RM437 mln hybrid solar project at Jus Dam (24 April 2026), Bernama