Malaysia to raise electricity tariff by 10% to 20% in 2014
In November 2013 Malaysia's energy minister signalled a 10%-20% electricity tariff rise for 2014. The background, Sabah's position, and the 1 January 2014 increase that followed.
In August 2012 Melaka broke ground on a 5 MWp, RM46 million solar farm at Rembia, built by state-owned Kumpulan Melaka Bhd. What was planned, the numbers checked, and what was built.
In August 2012 the Melaka state government broke ground on what it described as the first solar farm in Malaysia to be built and operated by a state government. The 5 MWp photovoltaic (PV) plant, costing RM46 million, was to rise at the Melaka World Solar Valley in the Rembia Industrial Area near Alor Gajah and sell all of its output to Tenaga Nasional Berhad (TNB) under the national feed-in tariff (FiT). This article sets out what was announced, checks the numbers that circulated at the time, and records what happened next.
The ground-breaking took place on 3 August 2012, and the New Straits Times reported it the next day. The key points were:
The plant was to be built in three phases:
| Phase | Capacity | Planned grid connection |
|---|---|---|
| 1 | 1.30 MWp | 15 December 2012 |
| 2 | 1.22 MWp | 15 January 2013 |
| 3 | 2.48 MWp | 15 February 2013 |
| Total | 5.00 MWp |
The Chief Minister was quoted as saying the plant would supply “17MW a day”, 514 MW a month and 6,162 MW a year. These are energy figures, so the correct units are megawatt-hours (MWh): about 17 MWh a day, 514 MWh a month and 6,162 MWh a year.
Dividing the annual estimate by the plant’s rating gives its expected specific yield:
6,162,000 kWh ÷ 5,000 kWp ≈ 1,232 kWh/kWp per year
1,232 ÷ 365 ≈ 3.4 kWh/kWp per day
That is a cautious but realistic figure for a ground-mounted plant on the west coast of the peninsula, and close to the 1,200 kWh/kWp per year that SEDA Malaysia used in its own FiT planning examples. For how location affects yield, see annual solar radiation in different Malaysian cities.
The same report gave the site as 7,248.43 hectares, which would be more than 72 square kilometres for a 5 MWp plant. That cannot be right: it would mean less than 1 kWp per hectare. The figure was almost certainly a misplaced decimal point. Later reports gave the site as about 7.2 hectares, or roughly 1.4 hectares per megawatt-peak.
A 5 MWp plant fell into SEDA’s “above 1 MW up to 10 MW” solar band, which carried much lower rates than home systems. SEDA’s basic rate for that band in 2013 was RM0.7600 per kWh, against RM1.1316 for rooftop systems of up to 4 kW. Bonuses for locally made modules and inverters were available, so the plant’s economics depended on scale rather than a premium rate. For the rooftop side of the scheme at the time, see homeowners can apply for solar rooftop FiT quota.
Yes, although later than first planned. Figures reported from the operator’s site information give the initial operation dates as:
| Phase | Capacity | Initial operation |
|---|---|---|
| 1 | 1.30 MWp | 11 April 2013 |
| 2 | 1.22 MWp | 16 May 2013 |
| 3 | 2.48 MWp | 2 August 2013 |
The same report gives the total investment as RM46 million, broken down as RM38 million for the PV system, RM2 million for infrastructure and RM6 million for land, with exports to TNB and a payback period of 12 years. Each phase therefore started about four to six months behind the schedule announced in 2012.
When the plant was announced, Malaysia’s FiT was less than a year old, having started on 1 December 2011. A state-owned company borrowing against a guaranteed 21-year tariff showed that a public body could treat a solar farm as a revenue-earning asset rather than a demonstration project. Melaka paired the plan with other green-technology projects, including the electric bus it launched in 2014.