The Green MechanicsEnergy, engineering and sustainable mobility

Kimanis RM1.5 billion gas-fired power plant: Sabah's 300 MW combined-cycle project

In March 2012 the RM1.5 billion, 300 MW Kimanis combined-cycle plant was in early construction beside Sabah's new gas terminal. Who owned it, how it worked, and why Sabah chose gas.

Line illustration for Malaysia Energy Archive

In March 2012, the drive south from Kota Kinabalu towards Papar and Beaufort passed a large construction site at Kimanis Bay. It was the start of the Kimanis power plant, a 300 MW gas-fired combined-cycle station costing about RM1.5 billion that was set to become the largest independent power plant in Sabah. Next to it, Petronas was preparing the site of a new onshore gas terminal that would land gas from offshore fields and supply the plant.

The project in early 2012

Item Detail (as reported 2011–2012)
Owner Kimanis Power Sdn Bhd, 60% Petronas Gas Berhad and 40% NRG Consortium (Sabah) Sdn Bhd, a Yayasan Sabah company
Capacity 300 MW, in three combined-cycle blocks of about 100 MW each
Main equipment Three GE Frame 6FA gas turbines with generators; GE also signed an 18-year service agreement
Fuel Natural gas from offshore Sabah, via the adjacent onshore terminal
Cost About RM1.5 billion; Petronas Gas planned to fund around 80% through project financing
EPCC contractor SCHB Engineering Services (a Suria Capital unit) with CTCI Corp and partners, under a RM1 billion contract
Basis Build, own, operate and transfer; power sold to Sabah Electricity Sdn Bhd (SESB)
Schedule GE’s 2011 announcement targeted commercial operation in the fourth quarter of 2013

GE noted that Sabah’s electricity demand was growing by more than 7% a year. With much of the state’s generation coming from ageing diesel and gas plants, supply interruptions and rationing were a live political issue (see our archive piece on Sabah’s power supply coverage targets).

Why gas, and why Kimanis

Kimanis was the answer to two problems. The first was the cancelled Lahad Datu coal plant. A proposed 300 MW coal-fired station on Sabah’s east coast had faced years of opposition from environmental groups and residents worried about its effects on nearby forest reserves and coastal ecosystems. After the Department of Environment rejected its detailed environmental impact assessment, Chief Minister Musa Aman announced on 16 February 2011 that the state would not proceed. The federal and state governments said they would pursue other sources, chiefly natural gas.

The second was the gas itself. Petronas’s Sabah–Sarawak Integrated Oil and Gas Project was bringing gas ashore at Kimanis to the new Sabah Oil and Gas Terminal (SOGT). From there, the roughly 500 km Sabah–Sarawak Gas Pipeline would carry gas to the LNG complex at Bintulu in Sarawak. Siting a power station beside the terminal let Sabah keep part of its own gas for local electricity rather than exporting all of it.

How a combined-cycle block works

Each Kimanis block pairs a gas turbine with a heat recovery steam generator (HRSG) and a steam turbine:

  1. The gas turbine compresses air, burns gas in it and expands the hot gases through a turbine that drives a generator.
  2. The turbine exhaust, still several hundred degrees Celsius, passes through the HRSG, which boils water into high-pressure steam.
  3. The steam drives a steam turbine and second generator, then is condensed and returned to the HRSG.

A simple illustration shows why this matters. Suppose the gas turbine converts 35% of the fuel’s energy to electricity, and the steam cycle recovers 30% of the remaining energy in the exhaust (illustrative figures):

Gas turbine:   0.35
Steam cycle:   (1 − 0.35) × 0.30 = 0.195
Combined:      0.35 + 0.195 ≈ 0.55  (about 55%)

The same gas therefore yields over half as much electricity again as an open-cycle turbine, with correspondingly lower fuel use and CO₂ per kWh. Compared with the diesel and heavy-oil sets that still supplied much of Sabah in 2012, combined-cycle gas was cheaper to run and markedly cleaner. Splitting the plant into three blocks also suited a small grid: one block can be taken down for maintenance, or trip, without losing the whole station.

What it meant for Sabah

The Kimanis plant was not renewable energy, and contemporary commentary noted that Sabah would still need to develop hydro, biomass, biogas and solar resources. But replacing a planned coal plant with efficient gas generation was a significant change of direction, and it placed new capacity on the west coast where demand was concentrated. For the state’s only large hydro station at the time, see Tenom Pangi; for the Bangladesh coal project TNB pursued after Lahad Datu, see TNB’s 1,320 MW Bangladesh bid.

What has changed since

  • Commissioning. The plant ran later than the original target. Its first two blocks entered operation in May and July 2014, and the third began commercial operation on 7 November 2014. Petronas said the three blocks together supplied about 285 MW to the Sabah grid, with SESB as the main customer. The plant was a key project under the government’s “Power Up Sabah” initiative.
  • The pipeline. The Sabah–Sarawak Gas Pipeline was commissioned in 2014 but suffered repeated leaks. In January 2025 Petronas announced that it would decommission the line, later clarifying that the decision affected the section running through Sarawak; Sabah’s government said the gas could be redirected to uses within the state.

Sources and further reading

  1. GE's Frame 6FA gas turbines help meet growing power needs in Sabah, Malaysia, GE press release (14 June 2011)
  2. Petronas Gas to raise funding for Kimanis plant, The Star (22 July 2011)
  3. Suria Capital unit and partners bag RM1bil job, The Star (14 January 2011)
  4. Sabah coal-powered plant plan is off, The Star via Eco-Business (17 February 2011)
  5. PETRONAS-Yayasan Sabah's joint venture power plant begins full operations, PETRONAS media release (9 November 2014)
  6. Malaysia's PETRONAS to decommission Sabah-Sarawak gas pipeline, The Star (29 January 2025)