Malaysia to raise electricity tariff by 10% to 20% in 2014
In November 2013 Malaysia's energy minister signalled a 10%-20% electricity tariff rise for 2014. The background, Sabah's position, and the 1 January 2014 increase that followed.
In March 2012 the RM1.5 billion, 300 MW Kimanis combined-cycle plant was in early construction beside Sabah's new gas terminal. Who owned it, how it worked, and why Sabah chose gas.
In March 2012, the drive south from Kota Kinabalu towards Papar and Beaufort passed a large construction site at Kimanis Bay. It was the start of the Kimanis power plant, a 300 MW gas-fired combined-cycle station costing about RM1.5 billion that was set to become the largest independent power plant in Sabah. Next to it, Petronas was preparing the site of a new onshore gas terminal that would land gas from offshore fields and supply the plant.
| Item | Detail (as reported 2011–2012) |
|---|---|
| Owner | Kimanis Power Sdn Bhd, 60% Petronas Gas Berhad and 40% NRG Consortium (Sabah) Sdn Bhd, a Yayasan Sabah company |
| Capacity | 300 MW, in three combined-cycle blocks of about 100 MW each |
| Main equipment | Three GE Frame 6FA gas turbines with generators; GE also signed an 18-year service agreement |
| Fuel | Natural gas from offshore Sabah, via the adjacent onshore terminal |
| Cost | About RM1.5 billion; Petronas Gas planned to fund around 80% through project financing |
| EPCC contractor | SCHB Engineering Services (a Suria Capital unit) with CTCI Corp and partners, under a RM1 billion contract |
| Basis | Build, own, operate and transfer; power sold to Sabah Electricity Sdn Bhd (SESB) |
| Schedule | GE’s 2011 announcement targeted commercial operation in the fourth quarter of 2013 |
GE noted that Sabah’s electricity demand was growing by more than 7% a year. With much of the state’s generation coming from ageing diesel and gas plants, supply interruptions and rationing were a live political issue (see our archive piece on Sabah’s power supply coverage targets).
Kimanis was the answer to two problems. The first was the cancelled Lahad Datu coal plant. A proposed 300 MW coal-fired station on Sabah’s east coast had faced years of opposition from environmental groups and residents worried about its effects on nearby forest reserves and coastal ecosystems. After the Department of Environment rejected its detailed environmental impact assessment, Chief Minister Musa Aman announced on 16 February 2011 that the state would not proceed. The federal and state governments said they would pursue other sources, chiefly natural gas.
The second was the gas itself. Petronas’s Sabah–Sarawak Integrated Oil and Gas Project was bringing gas ashore at Kimanis to the new Sabah Oil and Gas Terminal (SOGT). From there, the roughly 500 km Sabah–Sarawak Gas Pipeline would carry gas to the LNG complex at Bintulu in Sarawak. Siting a power station beside the terminal let Sabah keep part of its own gas for local electricity rather than exporting all of it.
Each Kimanis block pairs a gas turbine with a heat recovery steam generator (HRSG) and a steam turbine:
A simple illustration shows why this matters. Suppose the gas turbine converts 35% of the fuel’s energy to electricity, and the steam cycle recovers 30% of the remaining energy in the exhaust (illustrative figures):
Gas turbine: 0.35
Steam cycle: (1 − 0.35) × 0.30 = 0.195
Combined: 0.35 + 0.195 ≈ 0.55 (about 55%)
The same gas therefore yields over half as much electricity again as an open-cycle turbine, with correspondingly lower fuel use and CO₂ per kWh. Compared with the diesel and heavy-oil sets that still supplied much of Sabah in 2012, combined-cycle gas was cheaper to run and markedly cleaner. Splitting the plant into three blocks also suited a small grid: one block can be taken down for maintenance, or trip, without losing the whole station.
The Kimanis plant was not renewable energy, and contemporary commentary noted that Sabah would still need to develop hydro, biomass, biogas and solar resources. But replacing a planned coal plant with efficient gas generation was a significant change of direction, and it placed new capacity on the west coast where demand was concentrated. For the state’s only large hydro station at the time, see Tenom Pangi; for the Bangladesh coal project TNB pursued after Lahad Datu, see TNB’s 1,320 MW Bangladesh bid.