Micro-hydro to benefit Kampung Tiku villagers in Penampang, Sabah
In January 2013 an NGO-led 5 kW micro-hydro scheme was launched for 18 families in Kampung Tiku, Sabah. How such schemes work, with the P = ρgQHη formula worked through.
In November 2013 SESB said its RM57 million upgrade of the Tenom Pangi run-of-river hydro station on the Padas River would lift capacity from 66 MW to 75 MW. What the work involved.
On 21 November 2013, Sabah Electricity Sdn Bhd (SESB) managing director Ir Haji Abdul Razak Sallim visited the Tenom Pangi hydro power station and said an upgrade was under way to raise its capacity from 66 MW to 75 MW. The Borneo Post reported that close to RM57 million had been approved for the work under the Tenth Malaysia Plan, and that the project was 47% complete. Tenom Pangi was then the only major hydroelectric station operating in Sabah.
Tenom Pangi sits on the Padas River near Tenom, roughly 120 km south of Kota Kinabalu, where the river cuts through a gorge on its way to Beaufort and the coast. Construction began in 1978 and the station entered service in 1984. It is a run-of-river scheme: a gated concrete weir diverts part of the river into the intake, and three Francis turbines, each rated 22 MW, generate electricity in a surface powerhouse. There is no large storage reservoir, so output follows the river’s flow.
Its long-term average output has been put at around 400 GWh a year. That implies a capacity factor of roughly 69%:
Maximum possible energy = 66 MW × 8,760 h ≈ 578 GWh per year
Capacity factor ≈ 400 GWh / 578 GWh ≈ 0.69
That is high for hydro and reflects Sabah’s year-round rainfall. It also made Tenom Pangi one of the cheapest and cleanest sources on a state grid that otherwise relied mainly on gas and diesel generation.
According to the Borneo Post’s report of the visit, the project had three parts:
| Component | Detail |
|---|---|
| Generating units | Raise each of the three units from 22 MW to 25 MW (66 MW to 75 MW in total) |
| Control system | Replace the original control system with a modern one giving faster operational response |
| Cooling system | Upgrade the station’s cooling system |
| Start | Works began in stages on 28 February 2011 |
| Target completion | End of 2015 |
| Progress | 47% (November 2013) |
| Approved funding | Close to RM57 million, under the Tenth Malaysia Plan |
SESB said the work would take time because the units had to be taken out of service one at a time, so that supply to consumers in Sabah and Labuan was not compromised. The project was also among those mentioned when the Prime Minister tabled Budget 2014. The utility used the visit to appeal for the river to be kept clean: debris and agricultural waste had forced the station to stop for cleaning in previous years, which reduced generating capacity at times when the Sabah grid had little reserve.
Adding 9 MW to a 30-year-old station is a classic hydro uprating. The water, the weir and the head are unchanged; the gain comes from equipment:
Because Tenom Pangi is run-of-river, the extra 9 MW is only useful when the Padas carries enough water to use it, typically in wetter months. The added energy per year is therefore smaller than 9 MW multiplied by the hours in a year. Even so, at roughly RM6.3 million per added megawatt (RM57 million / 9 MW, and the budget also covered controls and cooling), uprating cost far less per megawatt than a new hydro scheme.
For the same equations at village scale, see our explainer on the Kampung Tiku micro-hydro scheme. For the thermal plant being built on Sabah’s west coast at the same time, see the Kimanis gas-fired power plant. Supply reliability in Sabah in this period is discussed in our guide to SAIDI.