The Green MechanicsEnergy, engineering and sustainable mobility

Frequently asked questions about solar PV systems for Malaysian homes (as of May 2013)

How rooftop PV works, how to size it, what it yields, and how the feed-in tariff paid Malaysian homeowners in May 2013, with a summary of how the answers changed under NEM and Solar ATAP.

Line illustration for Renewable Energy

By May 2013 Malaysia’s feed-in tariff (FiT) had been running for 18 months, but many homeowners were still unsure how a photovoltaic (PV) system worked or what it would earn. The answers below describe the rules and rates as they stood in May 2013 in Peninsular Malaysia. The rules have changed several times since, and a summary of those changes is at the end.

How a PV system works

What is a grid-connected solar PV system?

PV modules on the roof convert sunlight directly into direct current (DC) electricity. An inverter converts that into alternating current (AC) at grid voltage and frequency. Around these sit the mounting structure, DC and AC cabling, isolators and protection devices, and, under the FiT, a separate revenue meter that records every kilowatt-hour (kWh) the system sends out. A grid-connected system has no batteries; if the grid fails, the inverter shuts down for safety.

Do I need full sun all day?

The roof needs an unobstructed view of the sky for most of the day. Shading from trees, water tanks or neighbouring buildings costs more output than its size suggests, because shading one part of a string of modules can pull down the whole string. Close to the equator the sun is high in the sky for much of the year, so roof orientation matters less than it does in Europe, and a low-pitched roof can work in most directions.

Sizing and yield

How big a system do I need, and will it fit?

Under the FiT, sizing was driven by roof area and budget rather than household consumption, because the system sold all its output to the utility. As a guide, with modules of about 15% efficiency:

Area per kWp = 1 kWp ÷ (0.15 × 1 kW/m²) ≈ 6.7 m²

so a 4 kWp system needs roughly 27 m² of suitable roof. SEDA’s brochure described the individual route for systems of up to 12 kW.

How much electricity will it produce?

SEDA’s planning figure was 1,200 kWh per kWp per year, about 3.3 kWh per kWp per day. A 5 kWp system would therefore generate about 5 × 1,200 ÷ 365 ≈ 16 kWh on an average day. Sunnier locations do better; see annual solar radiation in different Malaysian cities.

The feed-in tariff in May 2013

What is the FiT, and since when?

The FiT began on 1 December 2011 when the Renewable Energy Act 2011 came into force. Distribution licensees such as Tenaga Nasional Berhad (TNB) must pay a fixed premium rate, set by SEDA Malaysia, for every kWh a registered renewable energy installation generates. For solar PV the rate is fixed for 21 years from the FiT commencement date.

How much would I be paid?

The rate depended on the system’s size band and the year it started generating. SEDA’s 2013 rates for individuals were:

Component RM per kWh (2013)
Basic rate, up to and including 4 kW 1.1316
Basic rate, above 4 kW up to 24 kW 1.1040
Bonus: installation in a building or building structure +0.2392
Bonus: use as building materials +0.2300
Bonus: locally made or assembled modules +0.0300
Bonus: locally made or assembled inverters +0.0100

An ordinary rooftop system therefore earned RM1.3708 per kWh up to 4 kW, or RM1.3432 per kWh for 4–24 kW, before any local-content bonus. The published rates for 2014 were already about 8% lower, so delay cost money.

What is the payback?

Worked example for a 4 kWp roof starting in 2013, using SEDA’s planning yield and the RM13,000 per kWp capital cost that SEDA’s brochure had assumed:

Annual generation: 4 kWp × 1,200 kWh/kWp = 4,800 kWh
Annual FiT income: 4,800 × RM1.3708 ≈ RM6,580 (about RM548 a month)
Simple payback:    RM52,000 ÷ RM6,580 ≈ 7.9 years

Lower prices or a sunnier roof shorten this; shading and financing costs lengthen it; see loans for home solar PV systems.

Can anyone apply?

Not freely. Capacity was released in quotas, and individuals applied online through SEDA’s e-FiT system when a window opened. In May 2013 SEDA’s website showed 2.97 MW of individual solar quota available for the first half of 2013 and 4.03 MW for the second half, and about 5 MW of individuals’ systems had been commissioned nationally. For the 2012 application round, see homeowners can apply for solar rooftop FiT quota.

What about Sabah?

In May 2013 the FiT was funded by a 1% surcharge on TNB customers’ bills in Peninsular Malaysia; domestic customers using 300 kWh a month or less were exempt. Sabah Electricity Sdn Bhd (SESB) customers did not yet contribute, so Sabah homes could not join. That changed on 1 January 2014; see rooftop solar under FiT for Sabah.

Ownership

How long does a system last?

Crystalline-silicon modules have no moving parts and are expected to outlast the 21-year FiT period. They lose output slowly: a review of nearly 2,000 measured degradation rates by the US National Renewable Energy Laboratory found a median of 0.5% a year. The inverter is the component most likely to need replacement during the FiT period, and should be budgeted for.

What maintenance is needed?

Very little: a periodic visual check, occasional cleaning where dirt builds up, and an electrical inspection of connections and isolators. Comparing monthly meter readings with expected output catches faults early.

Is it safe?

A PV array produces DC voltage whenever light falls on it, and it cannot simply be switched off at the modules. Installation must follow the utility’s interconnection requirements, and under the FiT the system had to pass an acceptance test verified by a Qualified Person before the tariff could start.

What has changed since

  • FiT to NEM (November 2016). New rooftop systems moved to net energy metering, which valued solar mainly by the bill savings from self-consumption. Exported energy was credited at a displaced-cost rate.
  • NEM 2.0 (January 2019). Exports were offset one-for-one against imported energy.
  • NEM 3.0 (2021 to June 2025). NEM Rakyat for homes opened on 1 February 2021, allowing up to 5 kW single-phase or 12.5 kW three-phase. Credits were offset against the bill for 10 years, with no cash payout. The programme ran until 30 June 2025.
  • Solar ATAP (from 1 January 2026). For TNB customers in Peninsular Malaysia, domestic systems are limited to 5 kW single-phase and 15 kW three-phase. Exports earn an energy offset for 10 years, after which the system is for self-consumption only.
  • Sabah. Sabah now has its own regulator, the Energy Commission of Sabah (ECoS). On 30 June 2026 ECoS launched Solar Rakyat Sabah, a 20 MW scheme for up to 4,000 homes. It allows up to 5 kWac single-phase and 10 kWac three-phase, with exports credited at the prevailing tariff under a 12-year contract with Sabah Electricity.

Today a system should be sized to match daytime consumption, and its value comes mainly from the electricity a household does not have to buy.

Sources and further reading

  1. SEDA Malaysia home page: 2013 and 2014 FiT rates, quota and announcements (archived May 2013), SEDA Malaysia
  2. Feed-in Tariff (FiT) in Malaysia brochure, SEDA Malaysia
  3. Surcharge on Electricity Bills for Renewable Energy Fund Revised from 1.0% to 1.6% (3 December 2013, archived), SEDA Malaysia
  4. Photovoltaic degradation rates: an analytical review (Jordan and Kurtz, Progress in Photovoltaics 21:12–29), NREL / Wiley
  5. Net Energy Metering (NEM) programme pages, SEDA Malaysia
  6. Solar Accelerated Transition Action Programme (Solar ATAP), SEDA Malaysia
  7. ECoS launches rooftop solar scheme for up to 4,000 Sabah homes (30 June 2026), The Star